Heavy Rigging & Jobsite Safety
Concrete Boom Pump Truck Outrigger Pad & Ground Bearing Pressure Calculator
Calculate concrete boom pump truck maximum outrigger reaction load (kips), required outrigger timber pad area (sq ft), and ground bearing capacity (psf) to prevent tip-over accidents.
Pump Truck Specifications
Square steel or composite outrigger pad
Max Outrigger Point Load
-- kips
0 lbs
Applied Ground Pressure
-- psf
Passes Allowable
Min Required Pad Size
-- x -- in
For allowable soil bearingCribbing & Rigging Safety Analysis
Timber Cribbing Mat Takeoff
-- Sq Ft
Cross-laminated hardwood crane mats
Full Boom Slew Stability Factor
1.50x FS
OSHA & ASME B30.27 CompliantASME B30.27 Pump Truck Safety Protocol:
Up to 80% to 90% of the entire truck weight plus the full concrete column in the delivery pipe can be transferred onto a single front outrigger during horizontal boom extension. Operating without adequate timber dunnage cribbing on soft soils causes punch-through ground failure, leading to catastrophic equipment turnover.